Corrected 5 October 2026. We said a Lismore to Bentley section was set to open and would extend the Casino to Lismore stretch. It had already opened, in 2024, and it is part of that stretch. Lismore City Council’s release, dated 12 December 2024 and republished on the trail’s site the next day, announced the opening of the 16.3 km Lismore to Bentley section that weekend, joining the 13.4 km Richmond Valley section to form a southern section of almost 30 km, and a later release on the trail’s site says the southern section was extended in 2024 to 29.7 km from Casino to Lismore. We also said the trail crosses four local government areas. The full corridor will, but the two open sections lie in three: Tweed, Richmond Valley and Lismore. What is still to be built runs through Byron Shire and Lismore; the Northern Rivers Rail Trail Supporters, in a release on the trail’s site, put it at 74 km of a 132 km trail and say a joint funding application from Byron and Lismore councils is awaiting a federal decision. The headline has been changed to match.

Updated 5 October 2026. That supporters’ release is dated 15 April 2026. Both councils have since announced that the joint $42 million application, to the Australian Government’s Regional Precincts and Partnerships Program, was unsuccessful: Byron Shire Council on 20 May 2026 and Lismore City Council on 21 May 2026. The unbuilt middle, its length and what each council has decided are in our follow-up, the rail trail’s missing middle.

Updated 17 October 2026. The body still said the trail crosses four local government areas and that the pages we read gave no total length, after the correction above said otherwise. The section on what is open now gives the three council areas of the open sections, with Byron Shire as the fourth member council, and the section on what is to come gives the 132 km and 74 km figures with their sources.

What is open

The trail is built along the region’s former rail corridor, and two sections are open. The northern one runs from Murwillumbah to Crabbes Creek, a distance the trail gives as 24 kilometres. The southern one runs from Casino to Lismore, given as 29.7 kilometres. Together that is close to 54 kilometres of the old line reopened as a path. The two open sections lie in three local government areas, Tweed Shire, Richmond Valley and Lismore City. Byron Shire is the fourth of the trail’s member councils, and the unbuilt stretch runs through it. The trail runs on Bundjalung land, which the trail and its member councils acknowledge.

Who paid, and the recognition it has drawn

The trail lists its support from both levels of government and beyond: the Australian Government, the NSW Government, the regional tourism body Destination North Coast, and the Northern Rivers Rail Trail Supporters. The recognition since it opened has been notable for a piece of infrastructure this new. The trail was awarded Gold in the Tourist Attraction category at the 2025 NSW Tourism Awards, and Silver at the 2025 Australian Tourism Awards, following a Silver at the 2024 Australian Tourism Awards the year before. It also holds Sustainable Tourism Accreditation and a TripAdvisor Travellers’ Choice award. Those tourism awards matter more than a self-issued badge would, because they are judged through an industry process rather than declared by the operator.

The visitor numbers, which are the trail’s own

The reason a rail trail is pitched as economic infrastructure and not just recreation is the visitors it brings through the towns along it. On the trail’s own figures, it reported more than 70,000 users in its first four months, and over 100,000 guests within seven months. Those are opening-period numbers reported by the operator rather than an independent count, and we flag them as such. Read with that caveat, they still describe a trail that was used heavily from the day it opened, which is the outcome the public money behind it was spent to achieve.

What is still to come

The corridor is not finished. The trail describes continuing conversations about future connections along the rest of the line. We first wrote here that a Lismore to Bentley section was still to open; as our correction above records, it opened in 2024 and is part of the Casino to Lismore stretch. Lismore City Council’s release and the trail’s supporters both give the finished trail as 132 kilometres from Murwillumbah to Casino, and the supporters put the unfinished section through Byron and Lismore at 74 kilometres. Those are the figures of a council and a campaign group, not an independent survey; we have not measured the corridor, and the two open sections plus that gap come to 127.7 kilometres, about four short of 132, which the releases do not explain. The shape of it is a staged build-out, in which more of the disused corridor is reclaimed section by section rather than all at once.

Our read

For a region whose recent story has been dominated by the 2022 floods and the long grind of recovery, the rail trail is a rare and largely unambiguous good-news asset: a corridor that would otherwise sit idle, turned into a drawcard that carries visitors through the towns of three council areas now, and of Byron Shire too if the corridor is finished. The honest qualifications are the two we have drawn out, that the headline visitor figures are the trail’s own and the timeline to finish the corridor is not yet pinned down in public. Set against those, the two open sections are real and substantial, the tourism recognition is externally judged, and the logic of finishing the line, more towns linked and the visitors spread further along them, is not hard to see. We will follow the funding for the next stages as it lands, and report it against what is promised here.

Related: The rail trail’s missing middle: the $42 million federal bid for part of it failed in May, and the program it went to is now paused.