Updated 27 November 2026. Councillors endorsed the exhibition unanimously on 26 November (resolution 261126/19, moved by Cr Kiri Dicker and seconded by Cr Michelle Bailey). They added a second part that was not in the officers’ recommendation: to Encourage property level flood resilience by including a property modification / resilience measure to the update of the Ballina flood risk management study and plan.
Source: the minutes of the 26 November 2026 ordinary meeting, read 27 November 2026. The minutes give no exhibition dates, and on 27 November the exhibition was not yet listed on Your Say Ballina; we will add the dates when it opens. We have past-tensed the descriptions, the standfirst and the section on what happens next to match.
What this is
Item 10.1 on the agenda for Ballina Shire Council’s 26 November 2026 ordinary
meeting asks councillors to endorse public exhibition of the Draft Ballina Island and West
Ballina Local Stormwater Management Study and Stormwater Masterplan, prepared by consultants
Engeny. It deals only with flooding from short, heavy rain inside the town, when the drains
cannot carry the runoff. It does not deal with the Richmond River or the ocean. The
consultants say so plainly:
Regional flood impacts far exceed the impacts of overland flooding.
It is the Ballina-town sequel to the overland studies for Lennox Head, Alstonville and Wardell, which went on exhibition in September and October (we covered Lennox Head’s here). The study’s budget is $120,000, funded two to one by the NSW Floodplain Management Program and the council, which by our arithmetic is $80,000 from the state and $40,000 from the council ($120,000 ÷ 3 = $40,000).
How big the problem is
The model puts the average cost of overland flood damage across the two suburbs at $4,150,136 a year, from 4,429 properties assessed. In a storm with a 1% chance in any year, 95 buildings flood above floor; in one with a 50% chance, 11 do. Twelve hot spots are listed, from Tamar, Grant and Bentinck streets on the island to Horizon Drive and Riverside Drive in West Ballina.
Why bigger pipes do not work here
Much of Ballina Island and West Ballina sits close to sea level. When the tide is high,
the pipe outlets are under water and stormwater has nowhere to go. The council’s
report puts it this way:
Without sufficient difference in level for water to drain by gravity, larger pipes alone are unlikely to resolve flooding.
Of the Skinner and Camden street hot spot the study says
Pipe upgrades alone will not resolve flooding in these areas, as their capacity is negated (drowned out) when outfalls are inundated by elevated tidal water levels.
Five pipe upgrades were tested anyway, at the hot spots where one looked plausible. Each was given a benefit cost ratio, the estimated flood damage avoided over 30 years divided by the cost of the work. Above 1, a project pays for itself. None comes close A.
| Pipe upgrade | Cost | Damage avoided a year | Ratio |
|---|---|---|---|
| Riverside Drive, West Ballina | $1,139,807 | $8,325 | 0.11 |
| Horizon Drive, West Ballina | $3,512,040 | $11,995 | 0.05 |
| Holden Lane, Ballina Island | $1,297,797 | $3,384 | 0.04 |
| Martin Street, Ballina Island | $1,561,873 | $0 | 0.00 |
| Tamar Street, Ballina Island | $473,711 | $0 | 0.00 |
| All five | $7,985,228 | $23,704 | 0.04 |
The “All five” row is ours. The costs add to $7,985,228; the yearly damage
avoided adds to $23,704, about 0.6% of the $4,150,136 baseline ($23,704 ÷ $4,150,136
= 0.0057); and the 30-year benefits add to $347,034 ($49,547 + $175,610 + $121,877), which
over $7,985,228 is a ratio of 0.04. The study’s own summary:
Three of the upgrade options demonstrated a reduction in flood impacts, but not to the extent that a positive Benefit Cost Ratio (BCR) was found.
The costs are early estimates, accurate to plus 100% or minus 50%, and exclude moving
underground services.
Exhibit A · from the source
For comparison, the Lennox Head study’s top-ranked option, a mobile pump at Tresise Place, scored 6.15 in the council’s 22 October report. Ballina Island is a different problem.
What the plan does first
Priority 1 is not a pipe. It is new flood gates on the drains at Grant Street, Kerr Street and Tamarind Drive ($123,284), and repairing the river wall between Cawarra Street and Bentinck Street to a level of 1.8 metres above the national height datum ($364,672): $487,956 together, with a ratio of 0.37. The gates stop a storm tide pushing back up the pipes into streets the river wall would otherwise protect. No new gates are proposed for West Ballina, where the study says a storm surge would come overland, in places from as low as 1.3 metres.
The study tested two storm tides. The lower, 1.6 metres, is about what was recorded across the area during Cyclone Alfred, which the study puts at 1.6 to 1.7 metres. At that level the package cuts the buildings flooded above floor from 55 to 54. At 1.8 metres, the existing river wall’s highest level, it cuts them from 213 to 190, 23 fewer, and avoids $2,254,891 of damage in that event.
Pump stations were ruled out:
Such infrastructure is beyond Council’s feasible financial capacity
.
So were big detention basins, for lack of fall and because the open space is all in
recreational use, and houses on raised stumps, because that leaves the tidal flooding in
place as sea levels rise.
The long-term plan is raising the ground
Ballina already requires new development in low areas to be filled to a minimum level.
The council’s report says many streets and some properties are already below king tide
level, and that sea levels are projected to rise about 20 centimetres by 2050 and up to 60
centimetres by 2100. The idea is that lots are raised as they are redeveloped, and roads and
drains follow. The report’s conclusion:
The assessment supports retaining Council’s current fill policy.
The catch is that every raised lot pushes the water it used to hold somewhere else. The
study modelled every private lot in the two suburbs filled to the required level and found
catchments where flood levels in the adjoining roads rise by more than 250 millimetres. It
warns that
there are areas where additional management measure will be required as the raising is implemented to protect properties that remain at the existing level.
The council’s report stresses that this is a very long-term scenario, that the model
leaves out the on-site stormwater measures new development normally has to provide, and that
as more lots are raised fewer buildings sit low enough to flood. Its remedy is further
sub-catchment studies, starting with high-risk parts of the Ballina Island CBD, to look at
on-site detention, controls on where and how much fill goes in, drainage upgrades and road
regrading. Those are listed as investigations, with no cost.
Raising the River Street and Kerr Street evacuation routes is priority 5. The modelling shows it would itself raise overland flood levels nearby, by up to 400 millimetres on the eastern side of the Kerr Street and Bangalow Road intersection if the roads went up to the climate-adjusted river flood level.
Loose ends in the papers
- The model is not calibrated. The study says
Calibration of the updated model was not undertaken as part of this Study.
It cites a lack of suitable historical flood data. The council’s report says results were compared with recorded flood heights where available, but that the March 2022 storm came on top of the February river flood, so some residents’ observations could not be tied to either. Hot spots were also checked against 31 questionnaire responses. The study uses version 4.1 of the national rainfall guidance, not 4.2, and floor levels from 1979 and 2009 surveys where it had them. - Eleven hot spots or twelve? The executive summary says the model
identified 11 flooding hotspots
; the hot spot table and the conclusion list twelve, as does the council’s report. - A copied sentence. The Tamar Street section reports its result as “the proposed Martin Street stormwater network upgrade”, the same words as the Martin Street section.
- A zero-benefit option still in the plan. The Martin Street upgrade,
$1,561,873, produced
No measurable flood level reduction
, yet the executive summary still lists it at priority 4:Implement the Martin Street drainage upgrade as a longer-term option, noting limited flood reduction benefits identified during the assessment.
The council’s own summary table presents priority 4 as investigation only.
The report also says the plan
does not represent a commitment by Council to fund or construct the identified works.
Our view
This is opinion, built on the documents above.
The study’s central finding is unwelcome and, on its own numbers, right: on low, tidal ground, money spent on bigger pipes mostly buys nothing. Saying so, rather than offering an $8 million works list, is the useful part of this document, and the flood gates and wall repair are the obvious first step: cheap next to the alternatives and aimed at the surge that actually comes up the pipes.
But the plan’s real strategy is raising Ballina one lot at a time, and its own modelling says that strategy moves water onto the neighbours who have not raised yet. The tools to manage that (on-site detention, fill controls, road regrading) are all still studies without a cost or a date. Residents in the high-risk catchments should be told when those studies will be done and what they will cost before they are asked to accept the fill policy as settled. And before the draft goes out, the council should tidy what it is exhibiting: an option its consultant found does nothing should not sit in the plan as something to implement, the hot spot count should agree with itself, and the exhibition material should say plainly, on the maps, that the model is uncalibrated.
What happens next
Councillors endorsed item 10.1 unanimously at the ordinary meeting on Thursday 26 November 2026, so the draft report and mapping go on the council’s website for comment, with a public information session during the exhibition. Neither the report nor the minutes give exhibition dates. We will add them when the exhibition opens.
How we sourced this
The decision before councillors, the policy background, the fill policy, the sea level figures and the project budget are from the officers’ report at item 10.1 of the agenda for Ballina Shire Council’s 26 November 2026 ordinary meeting (pages 93 to 107). Everything else, including the damage estimates, the hot spots, the five options, their costs and ratios, the flood gate results, the cumulative fill assessment and the limitations, is from the Engeny report itself, dated 9 October 2026 and published as the attachment to that item (pages 305 to 635 of the attachments file). We read the report text end to end and checked the benefit cost tables against the rendered pages. The “All five” row, the 0.6% share, the aggregate ratio and the $80,000 and $40,000 split are our arithmetic, shown in the text; we read “2:1” as two parts state to one part council. The study counts damage to buildings only, so works that mainly keep water off roads score low. The Lennox Head comparison is from the council’s 22 October 2026 report on that study. We have not named private addresses or businesses at the hot spots. We have not contacted the council.
Sources
The working. AI read the documents and drafted this story, under rules people set and answer for, working from the primary sources below. 13 quotations were compared by machine with our saved copies of the sources, and matched exactly. How we work.
- Ballina Shire Council, Minutes, Ordinary Meeting, 26 November 2026 (PDF, 14 pages, read 27 November 2026): item 10.1, resolution 261126/19 (page 11).
- Ballina Shire Council, Agenda, Ordinary Meeting, 26 November 2026 (PDF, 126 pages, read 21 November 2026): item 10.1, Ballina Island and West Ballina Local Stormwater Management Study and Stormwater Masterplan, including Table 1, the implementation plan.
- Ballina Shire Council, Attachments excluded from the agenda, Ordinary Meeting, 26 November 2026 (PDF, 635 pages, read 21 November 2026): item 10.1 attachment, Draft Ballina Island and West Ballina Local Stormwater Management Study and Stormwater Masterplan by Engeny, revision 2, 9 October 2026 (pages 305 to 635). Shown in Exhibit A.
- Ballina Shire Council, Agenda, Ordinary Meeting, 22 October 2026 (PDF, read 29 October 2026, re-checked 21 November 2026): item 10.1, Overland Flood Study - Lennox Head, Table 1, for the 6.15 ratio.
Live near one of the hot spots, or read the study differently? Tell us and we will check it against the council’s own papers and log the outcome.