What councillors asked
On 14 April 2026 the council resolved (52/26, 9-1, Cr Waters against) to investigate why
many approved subdivisions and residential developments are not being built, to look for
room to reduce developer contribution rates, and to
report to Council within the next 3 months on the number of developments in Lismore that have been approved but not acted upon and possible contributions discounts we can offer
.
The motion, from Crs Battista and Bing, said the contributions the council charges range from
$30,000 to $60,000 per residential lot.
Developer contributions are the charges a council levies on new development to pay for the infrastructure it will need. Lismore has two kinds: Section 64 charges for water and sewer, and Section 7.11 charges for everything else, such as roads and open space.
What the count found
Item 9.2 on the 10 November agenda is the report-back, seven months after the April vote. Staff counted every development approved between January 2021 and July 2026 that would create at least five homes or lots, from subdivisions and townhouses to flats, group homes and worker accommodation. Five years is the usual life of a consent, which set the window.
- 32 approvals, for 1,084 homes or lots in total.
- 22 have progressed, covering 882 homes or lots. That is about 69 per cent of the approvals and 81 per cent of the homes or lots.
- 10 have not started. By subtraction they account for 202 homes or lots.
“Progressed” is broad. The report counts a project that has paid significant
contributions or bonds, or taken out construction permits, alongside those with work under way
or finished. Projects are built in stages, so the 882 is the full yield of the 22 approvals,
not homes already standing. The report does not name the 10 stalled projects or say why each
has not started; it says the reasons
relate generally to market conditions, development feasibility and the option of applying developer contributions
,
and leaves the detail to a councillor briefing.
Why no discount now
Staff say any further discount is
expected to have significant impact on infrastructure delivery and financial sustainability
.
The council’s finance team adds that the council
would not normally have the capacity to provide a general contribution discount, at this time
A,
though it suggests looking at cases one by one. Both contribution plans are due to be redone in
2027, and staff propose weighing discounts then. The report lists what the council already
does instead: faster assessments, simpler planning processes, deferring contribution invoices
to later in a project, and marketing development sites.
Exhibit A · from the source
The recommendation is that the council note the report and receive a briefing on development feasibility and contributions before the end of the year. The report puts no dollar figure on what a general discount would cost the council.
The discount Lismore already gives
The next item, 9.3, reports on the one discount in force. Since June 2025 the council has waived 100 per cent of Section 64 and Section 7.11 charges on secondary dwellings in sewered areas, and on housing lodged by local not-for-profit groups, until 30 June 2027. In 2025-26, 10 secondary dwellings were approved under it and $68,616.53 was waived, about $6,900 a dwelling. No not-for-profit group applied. The council had asked for reports every six months; staff say the first was delayed by resourcing, so this one covers the whole first year.
Our view
This is opinion, built on the documents above.
The count is worth having, and it cuts against the premise of the motion: most approved housing in Lismore is moving, by the report’s generous measure. But the two questions that drove the April vote, why the other ten are stuck and what a cut would cost, have gone to a briefing and to 2027 rather than into the public report. A ratepayer cannot judge the trade-off staff describe without its size. The secondary-dwelling waiver shows what a narrow discount buys: ten granny flats for $68,616.53 of forgone charges in a year. Before the 2027 plans are drafted, the council should publish the same kind of figure for the wider options: what each one would cost, and how many of the 202 stalled homes or lots it might plausibly unlock.
How we sourced this
The analysis, figures, finance comment and recommendations are from items 9.2 and 9.3 of the 10 November 2026 agenda. The April resolution, its vote and its movers are from the 14 April 2026 minutes; the $30,000 to $60,000 range is the councillors’ own figure, from their motion in the 14 April agenda, and we have not checked it against the contribution plans. The 202 and the per-dwelling average are our arithmetic from the report’s figures. We have not contacted the council. The meeting is on 10 November; what councillors decide may differ from the recommendation.
Sources
The working. AI read the documents and drafted this story, under rules people set and answer for, working from the primary sources below. 5 quotations were compared by machine with our saved copies of the sources, and matched exactly. How we work.
- Lismore City Council, Agenda, Ordinary Meeting, 10 November 2026 (PDF, read 8 November 2026): item 9.2, Development Feasibility and Contributions; item 9.3, Monitoring of Developer Contribution Discounts for Secondary Dwellings. Shown in Exhibit A.
- Lismore City Council, Minutes, Ordinary Meeting, 14 April 2026 (PDF, read 8 November 2026): item 11.2, resolution 52/26 and the vote.
- Lismore City Council, Agenda, Ordinary Meeting, 14 April 2026 (PDF, read 8 November 2026): item 11.2, Residential Land Development Incentive Scheme Feasibility, the notice of motion and officer comment.
- Lismore City Council, Minutes, Ordinary Meeting, 10 November 2026 (PDF, read 13 November 2026): item 9.2, resolution 141/26; item 9.3, resolution 142/26; the votes.
What councillors decided on 10 November is in the update at the top of this page.
Building in Lismore, or read these papers differently? Tell us and we will check it against the council’s own papers and log the outcome.