What councillors were asked
The officer comment on item 11.5 of the
10 November agenda
sets out where things stand:
At the July 2026 Council meeting it was resolved that the Flood Risk Management Plan (FRMP) should be updated to acknowledge the bundle 2 mitigation measures.
Staff expect a draft plan, public engagement on it and adoption in early 2027.
Cr Virginia Waters gave notice of a motion that the plan
not be updated to include the mitigation measures identified by the final CSIRO report until such time the feasibility study be completed, the full inundation mapping has been publicly released and consultation with affected communities has been undertaken
.
Her notice says the mapping showing potential impacts on upstream communities has not been
released, and that three community members raised concerns about homes, farms and businesses
at the August meeting.
The feasibility study she refers to is the NSW Reconstruction Authority’s
Richmond River Technical Feasibility Study.
The Authority’s page, last updated 3 September 2026, says it is still planning the
study before appointing a consultancy, and that it will assess
technical, environmental, agricultural, economic, social, and cultural considerations
.
The minutes of the 10 November meeting were not published when we checked on 11 November,
so we do not yet know how the motion fared.
What the ten basins are
The measures come from CSIRO’s final report for the Northern Rivers Resilience Initiative, published by the National Emergency Management Agency on 30 June 2026. Each basin is a wall across a creek with gates that stay open in normal flows and close in a flood to hold water back, then release it once the peak has passed. Table 4 of the report sizes them:
- Six upstream of Lismore: Rock Valley (94.3 gigalitres), Corndale (91.3), Booyong (82.8), Goolmangar (53.9), Dunoon (43.0) and Bentley (40.7).
- Four upstream of Casino: Eden (69.4), Collins Valley (39.5), Fawcetts (39.2) and Barlings (11.3).
- Walls from 5 metres (Barlings) to 42 metres (Dunoon) high, measured from the bottom of the stream, and from 150 to 658 metres wide.
By our sum that is 565.4 gigalitres of storage in all, 406.0 of it above
Lismore. Bundle 2 also reopens Boundary Creek to the ocean, upgrades the Tuckombil and Tuckean
Swamp barrages, and adds a side dyke at Corndale. CSIRO further recommends investigating two
more basins, on Gradys Creek and Tuntable Creek, which its report says
were not suggested or discussed during stakeholder consultations but were identified after completing the simulations
.
What they would have done in 2022
Replayed against the 28 February 2022 flood, Bundle 2 lowers the modelled peak at the Lismore gauge from 14.87 metres to 12.80 metres, which the report says is still over the 10.65-metre CBD levee. For the 31 March 2022 flood it lowers 11.02 metres to 9.30, under the levee; for 2017, 11.72 metres to 10.32.
The cost of that falls upstream and over time. In the February event almost every basin filled: 403 gigalitres had to be let out on the Lismore side and 159 on the Casino side. Booyong took 15.0 days to empty, and under Bundle 2 the Lismore gauge took 17.0 days from the peak to fall below minor flood level. The report gives no figure for how long that took in the actual 2022 flood, so that number cannot be compared.
What the report does not say
The report describes the land behind the walls in one sentence, about its own aerial map of the full storages: A
Exhibit A · from the source
“Relatively small” is not given a number. The report states no area for any
storage, and the words “property”, “homes”, “landholder”
and “compensation” appear nowhere in it except a liability disclaimer. Its maps
show depth rising inside the detention areas in every modelled flood, at catchment scale.
NEMA’s own question-and-answer sheet says the model
may not be the most appropriate model when it comes to town/small area planning
.
CSIRO says the rest is outside its brief: a business case, cost-benefit analysis,
environmental approvals and detailed design are all still to come.
Our view
This is opinion, built on the documents above.
The CSIRO work is the best evidence the catchment has had, and a two-metre cut in a 14.87-metre flood is worth chasing. But the motion’s central complaint stands up on the documents. The only public account of what ten basins holding 565.4 gigalitres would cover is one unquantified sentence and a catchment-scale map, and the agency that published it says the model is not built for that scale of question. Writing the measures into a statutory plan, even as an acknowledgement, before anyone has said how many hectares or homes sit inside each storage hands upstream landholders the worry without the facts. The council’s own process puts public engagement on the draft plan in early 2027. That draft should carry the storage extents, basin by basin, as numbers: CSIRO mapped the full storages in its Figure 11, so the outlines exist.
How we sourced this
Basin capacities, wall heights and widths are from Table 4 of the CSIRO report; gauge peaks from Table 7; detained volumes, emptying times and days to minor flood level from Table 6 and section 3.2. Which basins sit above Lismore and which above Casino follows the report’s control-gauge labels in Table 6. The totals of 565.4 and 406.0 gigalitres are our sums of Table 4. The absence of an area or property count is from a text search of the full report for those terms and a read of every table. The July resolution is as quoted in the officer comment on the 10 November agenda; we have not read the July minutes. We have not contacted the council, CSIRO or the Reconstruction Authority.
Sources
The working. AI read the documents and drafted this story, under rules people set and answer for, working from the primary sources below. 5 quotations were compared by machine with our saved copies of the sources, and matched exactly. How we work.
- CSIRO (Vaze J and others), Scenario testing and recommendations for future flood mitigation activities in the Richmond River catchment, report for NEMA, 30 June 2026 (PDF, 90 pages, read 11 November 2026). Shown in Exhibit A.
- National Emergency Management Agency, Northern Rivers Resilience Initiative, Frequently Asked Questions, final report, 30 June 2026 (PDF, read 11 November 2026).
- Lismore City Council, Agenda, Ordinary Meeting, 10 November 2026 (PDF, read 11 November 2026): item 11.5, Lismore Flood Risk Management Plan and CSIRO NRRI, notice of motion and officer comment.
- NSW Reconstruction Authority, Richmond River Technical Feasibility Study, last updated 3 September 2026 (read 11 November 2026).
- Lismore City Council, Minutes, Ordinary Meeting, 10 November 2026 (PDF, read 13 November 2026): item 11.5, resolution 137/26 and the vote.
What councillors decided on the motion is in the update at the top of this page.
Live or farm upstream of one of these sites, or read the report differently? Tell us and we will check it against the source documents and log the outcome.